Dear Zoe,
Welcome to the latest construction update for your beautiful new home at Augusta by Mosaic. I hope this finds you and your loved ones well and you had a wonderful Easter break.
This month's update is particularly exciting as we will now witness Augusta's beauty gradually unveiled with the removal of scaffolding.
This pivotal stage marks a momentous step forward in the construction journey as the vision for Augusta becomes a tangible reality.
Despite battling persistent wet weather conditions, Mosaic Construction has been working exceptionally hard to maintain Augusta's program and headway.
In addition to scaffold removal commencing, March witnessed the team complete wall framing to Level 13 and wall sheeting and setting to Level 10.
Wet area tiling is progressing to Level 9, painting is advancing to Levels 1 through 8, and plumbing fixtures and fittings installation is moving through Levels 1 to 5.
Stone benchtop fit-outs are now at Level 6, and appliance installation has started on Level 3.
Further to continuing the above works, Mosaic Construction aims to complete carpet laying to Levels 1 through 5 in April, close out the required prep work for air conditioning system implementation to start, and advance final internal finishing works to the lower levels.
|