Dear Valued Stakeholder,

 

We hope this finds you well.

 

Please find following the latest construction progress update for The Bedford by Mosaic at 16-30 Prospect Street, Kangaroo Point.

 

We continue to progress key building works across multiple levels, with the tower structure now at Level 4.

 

Deliveries and heavy vehicle movements to and from the site will continue and be managed in accordance with the approved Traffic Management Plan. Traffic controllers will be in place during site hours to ensure the safe movement of vehicles and pedestrians in the surrounding area.

 

Construction activity will remain within approved standard hours of 6:30am to 6:30pm, Monday to Saturday.

 

Separately, Energex is anticipated to commence electrical infrastructure works along the northern side of Ferry Street later this month. Further information regarding the timing and duration of these works will be provided closer to commencement.

 

If you have any questions or concerns, we welcome you to reach out at any time by calling 1300 336 989 or emailing using the details below. 

 

If you are a Body Corporate or Building Manager in the Prospect Street area, we kindly ask that you please pass this information on to your building's occupants.

 

Kind Regards,

Stuart Firth
Project Manager - Mosaic Construction
P 07 3171 2270
A 89 McLachlan Street Fortitude Valley QLD 4006
E sfirth@mosaicconstruction.com.au | W mosaicproperty.com.au

Mosaic Property Group   Levels 5 & 6, 89 McLachlan Street    Fortitude Valley  QLD   4006   Australia

Click here to unsubscribe or to change your Subscription Preferences.