Dear Zoe,
Welcome to the latest construction update for your beautiful Masterpiece Series home at Florence by Mosaic. I hope this finds you and your loved ones well and that you had a wonderful Easter break.
This month's update is particularly exciting as we will now witness Florence's beauty progressively revealed with the removal of scaffolding.
This pivotal stage marks a momentous step forward in the construction journey as the vision for Florence becomes a tangible reality.
Despite battling persistent wet weather conditions, Mosaic Construction has been working exceptionally hard to maintain Florence's program and headway.
In addition to scaffold removal commencing, March witnessed the significant milestone of Florence's roof installation and completion of lift works.
Wall framing is now at Level 9 while sheeting is progressing to Level 8, and sanding and setting are following closely behind.
Wet area tiling is advancing to the lower levels, reaching Level 3 in March, along with wall painting.
In more good news, joinery and stone benchtop fit-outs are underway on Level 2, while glazing installation has started on Ground. Furthermore, the elegant timber-look balcony soffits are now being installed on all levels.
Externally, render and paintwork are ongoing on the facade and feature planter boxes. If weather permits, landscaping of these boxes is due to begin this month.
April will also see Mosaic Construction continue with internal fit-outs and private balcony works.
|