Dear Valued Stakeholder,
Welcome to the latest progress update for your beautiful home at The Prescott by Mosaic. I hope this finds you and your loved ones well and you had a wonderful Easter break.
Despite battling persistent wet weather conditions, Mosaic Construction has worked exceptionally hard to maintain The Prescott's program and headway.
In great news, March saw the team complete the Level 2 concrete slab pour, which again took place in two parts due to scale (a combined 1320m3 of concrete for both pours).
Following this, Mosaic Construction also formed and completed the first of the two concrete slab pours for Level 3.
Underground, the team removed all the temporary back props from Basement 2. These supports are no longer necessary for maintaining the structure while the concrete sets, signalling the progression to the next phase of work in this area.
If all goes according to plan, and weather permitting, the team will accomplish the second Level 3 concrete slab pour in addition to both Level 4 slab pours in April.
I will be back in touch in early May with another update. Feel free to reach out to me with any questions in the meantime.
Kind Regards,
|