Dear Valued Stakeholder,
Welcome to the latest progress update for your beautiful home at The Manning by Mosaic. I hope this finds you and your loved ones well and you had a wonderful Easter break.
Despite battling persistent wet weather conditions, Mosaic Construction has worked exceptionally hard to maintain The Manning's program and headway.
In great news, March saw the team accomplish the Level 3 concrete slab pour as planned. Due to its scale, two pours were required to complete this task.
In addition, following the above, Mosaic Construction progressed preparations for the Level 4 slab. This will also take place over two pours, the first of which is due imminently, weather permitting.
Further, the site's hoist was installed last month. This motorised pulley system will help move materials and equipment safely and efficiently between levels when the team starts interior works.
Should all go to plan, and again, weather permitting, the team will target the second of the two Level 4 concrete slab pours in April, after which they will advance preparations for the Level 5 slab.
I will be back in touch in early May with another update. Feel free to reach out to me with any questions in the meantime.
Kind Regards,
|