Dear Valued Stakeholder,
Welcome to the latest construction update for your beautiful home at Marella by Mosaic. We hope this update finds you and your loved ones well and you had a wonderful Easter break.
Despite battling persistent wet weather conditions, Mosaic Construction has worked exceptionally hard to maintain Marella's program and headway.
In great news, March saw the team reach the structural halfway point at Level 15, while progressing the jump form to Level 19.
Glazing installation has reached Level 12, and the effect is truly stunning. Marella is so distinct and elegant against the backdrop of the surrounding urban landscape.
Wall framing is advancing to Level 9, services rough-in is at Level 8, and wall and ceiling sheeting is at Level 7.
In the meantime, internal wall painting is moving ahead on Level 5, as is balcony and wet area waterproofing.
Tiling and flooring prep have kicked off on Levels 3 and 4, and, as a sign that these internal spaces are really starting to come to life, joinery fit-out has begun on Level 2.
Weather permitting, in addition to continuing to push ahead with the above internal works, Mosaic Construction is targeting completing the Level 17 concrete slab in April.
I will be back in touch in early May with another update. Feel free to reach out to me with any questions in the meantime.
Kind Regards,
|