Dear Valued Stakeholder,
Welcome to the latest construction update for your beautiful home at The Witton by Mosaic. I hope this update finds you and your loved ones well and you had a wonderful Easter break.
Despite battling persistent wet weather conditions, Mosaic Construction has worked exceptionally hard to maintain The Witton's program and headway.
In great news, March saw the team achieve structural top out at The Witton Two, located at the front of the site on Finney Road.
At the same time, The Witton One's distinctive 'crown' installation kicked off as planned, with the structural precast elements intricately linked to the V columns being lifted into position by crane.
Staying at The Witton One, preparation work for the rooftop pool was finalised in March, while internally, flooring installation is pushing ahead on Level 4, and balcony tiling is at Level 7.
Weather permitting, April sees the team targeting the accomplishment of several milestones. Most notably, following the finalisation of the crown installation, Mosaic Construction will begin the incremental dismantling of The Witton One's scaffold.
This pivotal stage marks a momentous step forward in the construction journey as the vision for The Witton is gradually unveiled as a tangible reality.
The team further aims to complete glazing installation on Level 15 at The Witton One while initiating lobby tiling.
Glazing fit-out will likewise progress at The Witton Two, in addition to finalising its sewer connection.
|