Dear Valued Stakeholder,
Welcome to the latest construction update for your beautiful home at Lily by Mosaic. I hope this update finds you and your loved ones well and you had a wonderful Easter break.
Despite battling persistent wet weather conditions, Mosaic Construction has worked exceptionally hard to maintain Lily's program and headway.
In great news, March saw the team complete both the Basement 1 concrete slab pour and the first of two concrete pours required for the Ground Level slab.
Shotcreting, the process of spraying concrete at high velocity onto a surface for reinforcement, was also successfully closed out for all Basement walls in March, as was removing the corner bracing (i.e. support beams required to ensure stability during basement works).
Weather permitting, Mosaic Construction will maintain its positive pace this month, completing the second Ground Level concrete slab pour and targeting the Level 1 slab pour.
I will be back in touch in early May with another update. Feel free to reach out to me with any questions in the meantime.
Kind Regards,
|