Dear Valued Stakeholder,
Welcome to the latest construction update for your beautiful home at Cotton Tree by Mosaic. I hope this update finds you and your loved ones well and you had a wonderful Easter break.
Despite battling persistent wet weather conditions, Mosaic Construction has worked exceptionally hard to maintain Cotton Tree's program and headway.
March saw the team persist with underground works to Building 2 (Memorial Avenue). In good news, the linkway tunnel, which Building 1 (The Esplanade) Residents will use to access the car park, was completed as planned.
Unfortunately, the ongoing inclement weather impeded Mosaic Construction's ability to complete the Basement 2 slab pour; however, they are ready to go as soon as the weather permits.
Following this, they will form and commence pouring the Basement 1 slab.
Simultaneously, the preparatory tasks for the Building 1 Level 2 concrete slab have been finalised. Once the team observes dry weather conditions, the pouring process will commence. Following this, they will proceed with forming the Level 3 slab.
I will be back in touch in early May with another update. Feel free to reach out to me with any questions in the meantime.
Kind Regards,
|